Acquiring land for rapid development will be one of Narendra Modi's biggest challenges
Many economists and industrialists hold that the new Land Acquisition Act is as much a deterrent to growth as the old one was. Many now expect Modi to come to the rescue of the industry with amendments to the Act. But the BJP supported the new Act in Parliament.

- Jun 4, 2014,
- Updated Jun 4, 2014 3:38 PM IST
Days before the Narendra Modi-led National Democratic Alliance (NDA) won the general elections, Ravi Uppal, Group Chief Executive Officer and Managing Director of Delhi-based Jindal Steel and Power Ltd (JSPL), heaved a sigh of relief. But this had nothing to do with Modi's imminent victory. Uppal was relieved because JSPL's Rs 30,000 crore project at Angul district in Odisha - a six million tonne steel plant - could now finally be fully commissioned.
The project had been ready for the past two years but some of the units could not be commissioned because JSPL was unable to get access to a three km stretch to connect a 25 km pipeline to the nearby Brahmani river. The remaining 22 km of the pipeline had long been laid. The company planned to draw water for the project from the Brahmani river through the pipeline.
But landowners had refused to give their land for the last mile connectivity. "They would do dharnas. Our requests to state authorities were neglected. We were left helpless," says Uppal. Finally, he managed to convince the local authorities to act. The police kept protesters at bay while the final stretch of pipeline was laid.*The story was written before Gopinath Munde, Minister of Rural Development, passed away in an accident on June 3, 2014.
Follow the authors at: @SunnySen; @sarikamalhotra2; @manukaushik
Days before the Narendra Modi-led National Democratic Alliance (NDA) won the general elections, Ravi Uppal, Group Chief Executive Officer and Managing Director of Delhi-based Jindal Steel and Power Ltd (JSPL), heaved a sigh of relief. But this had nothing to do with Modi's imminent victory. Uppal was relieved because JSPL's Rs 30,000 crore project at Angul district in Odisha - a six million tonne steel plant - could now finally be fully commissioned.
The project had been ready for the past two years but some of the units could not be commissioned because JSPL was unable to get access to a three km stretch to connect a 25 km pipeline to the nearby Brahmani river. The remaining 22 km of the pipeline had long been laid. The company planned to draw water for the project from the Brahmani river through the pipeline.
But landowners had refused to give their land for the last mile connectivity. "They would do dharnas. Our requests to state authorities were neglected. We were left helpless," says Uppal. Finally, he managed to convince the local authorities to act. The police kept protesters at bay while the final stretch of pipeline was laid.*The story was written before Gopinath Munde, Minister of Rural Development, passed away in an accident on June 3, 2014.
Follow the authors at: @SunnySen; @sarikamalhotra2; @manukaushik