'Huge Setback': NASA's Artemis mission delayed, Moon landing pushed to 2027

Produced by: Tarun Mishra

Artemis Program  Faces Setbacks

NASA has announced significant delays in its Artemis program, affecting the timeline for astronaut missions to the Moon. Artemis II, initially scheduled for late 2024, is now slated for April 2026, while Artemis III’s lunar landing is pushed to mid-2027.

Artemis II Mission Details

The Artemis II mission, carrying four astronauts, aims to orbit the Moon without a surface landing. This mission's new launch date comes after a prior delay from November 2024 to September 2025.

Issues with the Orion  Crew Capsule

The delays stem from problems with the Orion crew capsule’s heat shield. During an uncrewed test flight in 2022, the heat shield sustained damage, including cracks and erosion, during re-entry into Earth’s atmosphere. This raised safety concerns for future crewed missions.

Revised Approach to  Heat Shield Design

NASA has decided to retain the current heat shield design to avoid further delays caused by a redesign. Instead, the capsule’s return trajectory will be modified for the Artemis II mission to mitigate risks.

Program Costs and  Challenges

The Artemis program, launched during former President Donald Trump’s administration, faces mounting costs and technical challenges. By 2025, the program's estimated cost will reach $93 billion, with each launch of the Space Launch System (SLS) priced at approximately $2 billion.

Strategic Importance  of Artemis

NASA Administrator Bill Nelson emphasized the program's importance in maintaining U.S. leadership in space exploration, particularly amid competition from China, which plans its own Moon missions by 2030.

International Collaboration through Artemis Accords

The Artemis Accords, a framework for global cooperation in lunar exploration, include India as a signatory, reflecting the program’s role in fostering international partnerships for space exploration.

Future Vision: Moon to Mars

The Artemis program’s long-term goals include establishing a permanent human presence on the Moon, developing lunar bases, and serving as a stepping stone for human exploration of Mars. Despite delays, NASA remains committed to achieving these objectives.