The critical coal stock position at thermal power plants across the country is likely to stabilise after about a month.
According to an official, the coal production at the mines of Eastern Coalfields (ECL), Bharat Coking Coal (BCCL) and Central Coalfields (CCL) is likely to improve only post the festive season.
"The festive season in the eastern part of the country is mainly a lean period, when these companies - ECL, BCCL, and CCL - are short-staffed," the official said, adding that the stock situation at the mines was likely to come under control from mid-October onwards.
Land acquisition problems, delays in getting environment and forest clearances and bottlenecks in coal transportation through railways have time and again affected fuel stocks at thermal power stations.
According to latest data released by Central Electricity Authority (CEA), which provides technical support base to the Ministry of Power, on September 14, 53 thermal plants have less than seven days of coal stocks at their disposal.
Of the 53 plants, 30 stations have less than four days of fuel available to them.
This situation, when compared to last month, has deteriorated. The number of power stations with less than a week's stock stood at 48, of which 24 had less than four days of coal, CEA data said.
The official said that the government had made available additional coal to the tune of 50 million tonnes (MT) from the Tori-Shivpuri-Kathotia mines in North Karanpura, Jharkhand.
Also the railway line connecting the coal mines at Manendragarh, Chhattisgarh had improved, which will help in the transportation of 20 MT fuel.
"All these measures put together the coal situation will improve by the middle of next month," the official added.
In July, of the 100 coal-based power plants monitored by the CEA, 44 power plants had critical coal stock of less than seven days requirement. About 25 had coal stock of less than four days requirement.